Energy · Benelux

380 kV cable corridor under a city street

Route width reduced 2.4 m

01 · Challenge

An underground high-voltage cable route risked exceeding limits at ground-floor apartments along the street.

02 · Simulation

Comparison of eight laying configurations including trefoil, flat, split-phase and shielded trough variants.

03 · Solution

A trefoil arrangement in a shielded concrete trough with a conductive cover plate.

04 · Execution

Detailed design handed over to the civil contractor with installation supervision.

05 · Result

Compliance achieved with a 2.4 m narrower corridor, saving significant excavation cost.

Start a project

Tell us the field level you need. We will tell you how to reach it.

A first assessment by one of our engineers is free of charge and usually takes less than 48 hours.